Can a Radial Gas Blower Run Without Flexible Couplings?

Patricia Callen10 min read
Application NoteOther ManufacturerOther Topic
Licensed PE Working through this on a live machine? A Maine-licensed engineer can take it from here — included with IMD hardware, by the hour for everything else. Book an engineer

The temporary rigid spool changes the load path: vibration, thermal growth, installation offset, and pipe movement that the flexible coupling would absorb can reach the blower casing, flanges, welds, supports, and bearings. The decision cannot rest on whether vibration feels weak by hand. Measure alignment, static flange reaction, vibration over the intended speed range, joint leakage, and pipe displacement before accepting even a temporary run.

What function is lost when the compensator is removed?

The installed devices are flexible pipe couplings, not pulsation dampers. Their job is to reduce mechanical vibration transmission and accommodate relative movement between each blower and the connected DN65 stainless-steel piping. Replacing them with welded rigid spools joins the machine and pipe into one mechanical system.

The pair of parallel, redundant radial blowers is rated for 120 Nm³/h at 20 mbar ΔP, with pipeline pressure reaching approximately 40–50 mbar above atmospheric pressure. Low pressure does not make the mechanical or hazardous-area risks negligible: a small leak can still release flammable gas, while cyclic displacement can reduce the fatigue life of a weld or flange without producing an immediate pressure-test failure.

A stainless-steel replacement compensator is not automatically interchangeable with the leaking thin-rubber design. Confirm its pressure rating, gas compatibility, allowable axial, lateral, and angular movement, effective spring rate, installation length, and any anchoring or restraint requirements. Material alone does not define flexibility.

Does the cold installation impose load on the blower?

Start with the system stopped, depressurized, isolated, and at a stable temperature. Measure the gap, parallel offset, and angular mismatch between mating flanges before pulling them together. If bolts must draw the pipe into position, the rigid spool will preload the blower nozzle and casing continuously.

Loosen the connection only under the approved isolation procedure and observe whether the pipe springs away, rotates, or changes elevation. A measurable release indicates stored pipe strain. Correct the spool geometry or pipe support arrangement before continuing; do not use flange bolts to force alignment.

Also inspect the blower base, hold-downs, shaft or impeller condition, and machine alignment. Changing flexible machine mounts to solid mounts without a calculated support design can merely redirect vibration into the casing or foundation. Likewise, loosening floor supports to create more movement replaces a defined restraint with an uncontrolled boundary condition. Either change requires an engineered support review and new alignment readings.

If the cold flanges mate freely and the machine alignment remains within the blower manufacturer's limit, continue to the run-up check. If those limits are unavailable, obtain them through the manufacturer's official support channel before approving the temporary spool.

What does a controlled VFD run-up reveal?

Look at the trend first. Record blower casing vibration, pressure-pipe vibration, bearing condition, pipe displacement, speed or drive frequency, suction pressure, discharge pressure, and gas-detector status from stopped condition through the proposed operating range. Use instruments at repeatable locations; a hand check cannot identify vibration amplitude, direction, or resonance.

A slow VFD ramp reduces a sudden startup torque or pressure step, but it does not remove imbalance, misalignment, pipe strain, or resonance. A slow sweep can also spend more time near a resonant frequency. Advance through controlled speed points, hold only long enough to obtain stable readings, and stop if vibration rises sharply, pipe motion grows, joints move, rubbing appears, or bearing behavior changes.

The observed pressure-pipe vibration was noticeable but weak at low power. That observation clears only that operating point. It does not qualify full speed, the complete operating envelope, simultaneous operation of both blowers, or a condition in which a downstream consumer changes gas flow.

If vibration remains stable and below the applicable machine and piping limits, proceed to containment checks. If a narrow speed band produces amplification, do not simply program the VFD to pass through it until the manufacturer and piping engineer review the measured data and confirm that transient passage is acceptable.

Which readings separate normal operation from a developing fault?

Signal Source or measurement point Wrong-value symptom and next decision
Machine vibration Repeatable points on the blower casing and bearing locations A step change or speed-dependent peak points to imbalance, misalignment, resonance, or transferred pipe load. Stop and compare cold alignment and pipe vibration.
Pipe vibration Suction and discharge pipe near each flange, arch, weld, and first restraint Growth away from the machine or concentrated movement at a support identifies a structural mode or poor restraint. Review supports before further run-up.
Static displacement Reference marks at blower flanges, free pipe sections, and anchors Permanent movement after shutdown indicates slip, yielding, or support movement. Remove the temporary spool and inspect alignment.
Differential pressure Suction and discharge pressure readings Failure to approach the expected operating duty, or unstable pressure, calls for airflow, valve, check-valve, and rotation checks before mechanical adjustments.
Joint leakage Approved leak-detection method at nearby flanges, gaskets, welds, and temporary-spool joints Any confirmed gas release ends the test. Isolate under the site emergency procedure and repair before retesting.
Bearing condition Blower bearing vibration, temperature, and sound A change correlated with pipe connection or speed can indicate casing distortion or alignment error. Stop and remove pipe load before inspecting the machine.
Gas alarm Installed room gas-warning system An alarm detects a hazardous condition but does not isolate the room automatically. Follow the shutdown, evacuation, and manual-isolation procedure.

Where will rigid-pipe stress concentrate?

The upstream pipe is bolted to the floor shortly before the blowers, so rigid connection can transmit nozzle movement into a short, stiff span. The downstream pipe has about 2 m without wall attachment and can move a few centimetres; that freedom may lower static restraint in one direction but can also create a flexible span with a resonant mode. The arches on both sides add geometric flexibility, yet their actual effect depends on leg length, wall thickness, support locations, and motion direction.

Inspect the first weld, flange, gasket, branch, arch, and restraint on each side of the operating blower. Mark flange-bolt positions and pipe reference points so small changes become visible. Check the idle parallel blower as well: common headers, check valves, and supports can transfer vibration or allow reverse-flow effects even when only one machine runs.

Do not clamp a vibrating span merely because movement is visible. An added clamp shifts forces into another weld, nozzle, or anchor and can raise natural frequency into the operating range. Have the piping engineer select temporary restraints from measured motion and calculated loads.

Can the hazardous-area controls tolerate a temporary leak path?

The room is described as Ex Zone 1 or 2; resolve that ambiguity from the classified-area dossier before commissioning. The blowers and other equipment are ATEX-rated, and a gas-warning system is installed, but rated equipment and detection do not prevent a release from a failed gasket, weld, or temporary connection.

There is no automatic room isolation. Before the trial, document who can stop the blower, which valves isolate the gas supply and discharge, where those valves are located, whether they remain accessible during an alarm, and how personnel leave the area without approaching the release. Test the stop command and confirm valve position indication where fitted.

Confirm the function and orientation of the wafer-style devices identified as check valves. A check valve limits reverse flow when it seats correctly; it is not a positive isolation valve and does not replace the emergency isolation plan. Commission one blower at a time unless operation of both is specifically required and the shared piping has been evaluated.

Which inspections belong before the first gas run?

Pressure testing and weld examination answer different questions. A pressure test checks containment under the specified test condition; it does not demonstrate acceptable vibration, fatigue life, nozzle loading, thermal movement, or gasket behavior after repeated cycles. Radiography examines selected weld volume but does not qualify unexamined welds or prove that the assembled pipe is free of harmful dynamic stress.

The proposed examination of 10% of welds, clustered near the blowers, may improve sampling around the highest-interest area, but performing it later leaves commissioning dependent on unexamined temporary work. Complete the inspection required by the approved piping quality plan before introducing flammable gas. Include the temporary spool welds and any joints whose fabrication or alignment changed.

Perform the planned pressure test after installing the temporary spool and repeat the specified test after fitting the permanent compensators. Use an approved leak-detection method at nearby flange gaskets before startup, after the first run, after thermal stabilization, and at a documented interval during temporary service. Leak spray is a local check, not a substitute for continuous gas monitoring or the site isolation procedure.

What temporary commissioning procedure controls the risk?

  1. Approve the temporary-spool design, hazardous-area work controls, inspection plan, operating envelope, and emergency isolation method. Record the temporary configuration and its removal date.
  2. Verify each blower's mechanical condition, rotation, base attachment, and alignment. Measure flange offset and pipe spring before bolting the spool into place.
  3. Complete required weld examination, pressure testing, and local leak testing before admitting process gas. Confirm that gas detection, stop commands, check valves, and manual isolation valves perform their assigned functions.
  4. Install vibration and displacement measurement points on both suction and discharge piping, the blower casing, nearby supports, and the idle parallel blower. Record a stopped baseline.
  5. Start one blower at minimum practical VFD output. Record speed, pressures, machine vibration, pipe vibration, displacement, bearing condition, and gas-detector status.
  6. Increase speed in controlled steps through the required operating range. Stop for a leak, alarm, rapidly rising vibration, pipe-support movement, joint movement, rubbing, or abnormal bearing behavior.
  7. Hold only approved operating points and test expected consumer changes. Do not extend acceptance from low power to full duty without measurements at full intended duty.
  8. After shutdown, repeat alignment references, flange and weld leak checks, bolt-position checks, and pipe-displacement readings. Trend every subsequent temporary operating period against this baseline.
  9. When the stainless-steel compensators arrive, verify their movement capability and installation length, remove the rigid spools, align the piping without forcing the flanges, and complete the specified pressure and leak tests.

How is the permanent repair verified?

After the compensators are installed, repeat the same VFD run-up with measurement points unchanged. Compare casing vibration, pipe vibration, bearing condition, differential pressure, and static displacement at matching operating points. A successful repair produces leak-free joints, stable alignment, no support movement, and vibration within the blower, coupling, and piping limits.

Inspect the compensators during operation for twisting, excessive axial compression, lateral offset, contact with adjacent parts, and clamp or flange movement. Recheck after shutdown for permanent set. If the metal compensator transmits more force than expected, review its spring rate, anchors, guides, and installation geometry rather than assuming stainless construction solved the load-path problem.

FAQ

Can I run a radial gas blower briefly without flexible couplings?

Only under an approved temporary configuration with free cold-flange alignment, pre-service weld and pressure checks, verified isolation, and measured vibration through the full intended VFD range. Weak vibration at low power does not approve full-duty operation.

Does a slow VFD ramp make rigid piping safe?

No. It reduces the startup step but cannot correct imbalance, misalignment, pipe strain, or resonance, and a slow ramp may dwell near a resonant speed. Record vibration versus speed and stop at any sharp increase.

Does a pressure test prove the temporary spool can withstand vibration?

No. The test demonstrates containment at its specified condition, while fatigue, nozzle load, resonance, and thermal displacement require alignment, vibration, and movement measurements. Complete the required weld examination before gas commissioning.

Can I continue if the pipe vibration still feels weak?

Stop immediately for a gas alarm, visible joint movement, rapidly rising vibration, rubbing, abnormal bearing behavior, or any loss of containment. Stop the trial if measured vibration or nozzle loading exceeds the blower or coupling manufacturer's limit, or if no approved limit is available for the temporary arrangement. Escalate the measured run-up data, pipe-restraint sketch, alignment readings, and temporary-spool design to the blower manufacturer or its official support channel before restarting.

Back to blog