Resolving SINAMICS G150 Fault F1370 (Motor Stalled) on Mains-to-Generator Changeover
The SINAMICS G150 cabinet drive reports fault F1370 – Motor stalled when the line supply is transferred from the utility mains to a standby generator while the drive is in AUTO (run) state and the induction motor is mechanically loaded. The fault is a logical consequence of the speed/load monitoring function tripping because the actual rotor speed falls below the configured threshold (p2163) for longer than the configured monitoring time (p2166) during the supply transfer transient. This reference describes the root cause, the exact parameter set that must be re-tuned, and the commissioning procedure required to make the changeover transparent to the process.
1. F1370 – Fault Mechanics
F1370 is raised by the closed-loop vector/sensorless control (SLVC, VC) of the Control Unit CU320-2 inside the G150 cabinet. The drive evaluates the difference between the speed setpoint n* and the actual speed n_act; if the deviation remains outside a programmable hysteresis band for a programmable time, the drive concludes that the motor has stalled and trips.
The underlying calculation uses the following Siemens monitoring chain (per the G150 List Manual, function block Speed/load monitoring):
n_act_low = |n_act| < p2163
n_act_high = |n_act| > p2163 + p2164
stalled = n_act_low AND (|i_act| > p2170) for time > p2166
On a mains-to-generator transfer the line voltage typically dips 10 – 20 % for 50 – 400 ms, the line frequency can shift by 0.5 – 2 Hz, and the DC-link voltage at the G150 follows with the same transient. While the DC link sags, the inverter output voltage collapses, the air-gap flux decays, the rotor slips heavily and the actual speed momentarily leaves the p2163 window. The drive's torque-producing current peaks as the controller tries to hold the speed setpoint; the combination of low speed + high current for > p2166 ms is the precise condition the firmware interprets as a stalled motor.
| Parameter | Description | Default (V5.1) | Recommended for generator transfer |
|---|---|---|---|
p2144 |
BI: Enable motor-stalled monitoring | 0 (OFF) | 1 (ON) – keep enabled for safety |
p2163 |
Speed threshold for stalled | 0.9 × n_rated | 0.6 – 0.7 × n_rated |
p2164 |
Hysteresis speed for stalled | 10 rpm | 20 – 30 rpm |
p2166 |
Monitoring time for stalled | 10 s | 1.5 – 3.0 s |
p2167 |
Off delay for stalled | 10 s | 0.5 – 1.0 s |
p2170 |
Current threshold for stalled | 1.0 × I_mot_rated | 1.1 – 1.2 × I_mot_rated |
r2169.7 |
BO: Status word, motor stalled (1 = stalled) | – | Map to SCC/PLC for diagnostics |
2. Root Cause on a Mains-to-Generator Changeover
The cabinet arrangement in a typical G150 application looks like this:
When the upstream ATS (Automatic Transfer Switch) reroutes the line, the G150 experiences the following sequence in < 500 ms:
- Loss of line (≥ 1 cycle): the Active Line Module / Basic Line Module inside the G150 latches the DC bus down to ~ 0 V because the pre-charge contactor cannot hold the bus against the load.
- Generator closure: voltage ramps up at the AVR-controlled rate (typ. 2 – 5 s). The G150 sees a slow, distorted, low-frequency supply.
- DC bus recovery: the new supply recharges the DC link; the inverter is unable to maintain rated flux for the first 1 – 3 cycles.
-
Speed collapse: the loaded motor decelerates by 5 – 15 % as the inverter momentarily saturates;
|n_act|leaves thep2163window. -
Fault trip: after
p2166the firmware raises F1370 and drops the inverter pulses via OFF1 / OFF3, depending onp0845/p0849configuration.
3. Pre-requisites Before Tuning
Before changing any parameter, the following items must be confirmed; the manual in the source link lists them as mandatory pre-conditions for any automatic restart work:
- The control mode (
p1300) is 20 (SLVC) or 21 (VC with encoder). F1370 only trips in these vector modes – the drive does not stall-monitor a pure V/f loop (p1300= 0/1/2/3) with the same code. - Quick commissioning (
p0010= 1) has been completed and a motor ID run (p1910= 1) has been performed. The motor equivalent-circuit data inp0350–p0369must be valid; otherwise the slip calculation used by the stall monitor is wrong. - The encoder (where fitted) is healthy:
r0458= 0xC0000000 andp0431is set to the correct PPR. - Power and signal grounds are tied to a single star point; the G150 cabinet ground must be < 1 Ω to the plant ground.
- The Run / Off logic has been validated.
p0840(ON/OFF1) andp0844(1st OFF2) must come from a stable source – toggling them during the changeover re-triggers the very problem you are trying to solve.
4. Flying Restart – the Primary Remedy
Flying restart (suchlauf) re-initialises the drive onto a still-spinning motor without first waiting for it to coast to zero. With p1200 active, when the line returns the drive does not attempt a normal ramp from 0 rpm; it searches for the rotor's actual speed and synchronises to it.
| Parameter | Function | Value to set | Notes |
|---|---|---|---|
p1200 |
Flying restart operating mode | 2 or 4 | 2 = after enable/OFF2; 4 = after ON command – preferred for AUTO changeover |
p1201 |
Flying restart enable signal source | r0863.0 (drive enable) | Do not tie to ON/OFF1 directly; tie to drive enable. |
p1202 |
Search current (% of motor rated) | 60 – 90 % | Higher = faster catch, larger torque ripple |
p1203 |
Search velocity factor (V/f) | 2.0 (default) | Increase to 3 – 4 for very slow coast-down loads |
p1204 |
Search velocity factor (SLVC) | 1.0 (default) | Adjust only if catch fails with default |
p1207 |
Acceleration time after catch | 0.5 – 2.0 s | Decide ramp back to setpoint |
p1208 |
Deceleration time for re-brake | 0.5 – 2.0 s | Not used in catch-up but kept for symmetry |
The recommended AUTO setting for a generator changeover is:
p1200[0] = 4 ; Flying restart active after ON command
p1201[0] = r0863.0
p1202[0] = 75 ; % of p0305
p1203[0] = 2.5
p1207[0] = 1.0 ; ramp back to setpoint
With p1200 = 4, the drive executes the search on every edge of the enable – exactly what is required when the line supply returns after the generator stabilises. Note that on some firmware lines (V4.7 SP3 and earlier) p1200 is a single index; on V5.1 it is indexed per drive object – use p1200[0] explicitly.
5. Automatic Restart – the Second Pillar
Flying restart alone re-synchronises the inverter to the rotor; it does not acknowledge faults. F1370, once raised, will keep the drive in trip state. The second piece of the solution is the automatic restart function (WRA – Wiederanlauf) that clears the fault, waits for the line to recover, and re-issues the run command.
| Parameter | Function | Value to set | Effect |
|---|---|---|---|
p1210 |
Automatic restart mode | 4 or 6 | 4 = restart after mains failure with fault ack; 6 = same + restart after any fault that allows auto-ack |
p1211 |
Number of start attempts | 3 – 5 | Restarts within p1213
|
p1212 |
Wait time between attempts | 3.0 s | Match the AVR ramp of the generator |
p1213 |
Restart monitoring time | 30 s | All p1211 attempts must succeed inside this window |
p1214 |
Restart fault handling | 1 | Continue attempts on F1370 |
p1215 |
BI: Enable motor-mounted brake | 0 | External brake, if fitted, must be released |
p1210 = 1 for a loaded process. p1210 = 1 acknowledges every fault without restarting; it masks the underlying F1370 instead of solving it. Use 4 or 6, which both issue a flying restart on the re-closure of the line.The sequence with p1200 = 4 and p1210 = 4 during a changeover is:
6. Line Supply Quality Parameters
If the generator set is undersized, F1370 will re-appear on the next changeover even with the restart set correctly. The G150 also reports line-quality faults F30002 (DC bus undervoltage) and F30003 (DC bus overvoltage) that often accompany F1370. Tune the line-quality thresholds before relying on p1200 / p1210:
| Parameter | Function | Default | Generator-tolerant setting |
|---|---|---|---|
p0210 |
Device supply voltage (V) | 400 / 480 / 690 | Match the generator setpoint exactly |
p0211 |
Supply frequency (Hz) | 50 / 60 | Match AVR; do not leave at default 50 if gen is 60 Hz |
p0280 |
DC-link undervoltage threshold | 1.42 × √2 × p0210 | 1.30 × √2 × p0210 – wider band |
p0282 |
Line frequency low threshold | –5 % | –10 % |
p0283 |
Line frequency high threshold | +5 % | +10 % |
p0284 |
DC-link overvoltage threshold | 1.15 × V_DC_rated | 1.20 × V_DC_rated |
p3450 |
Line phase rotation monitor | 1 (CW only) | 0 (off) only if generator rotation can be checked manually |
p3450 = 1.7. Voltage Sensing Module (VSM10) Configuration
G150 drives with line-side Active Line Modules are equipped with a VSM10 mounted on the cabinet roof or on the line filter. The VSM10 measures the line voltage and supplies it to the Active Line Module for synchronisation. Its presence and wiring must be confirmed for the changeover to be clean:
-
p0140= number of VSM10s installed (typically 1). -
p0141= 999 (free topology) for the VSM10. -
r0190bit 0 must show 1 after a power-on; bit 0 = 0 means the VSM is not seen and the Active Line Module falls back to uncontrolled pre-charge, which is exactly what you do not want on a generator transfer.
8. Step-by-Step Commissioning Procedure
- Switch the G150 to local mode, raise the speed to 25 % rated, hold for 30 s, and verify the actual current does not exceed
p2170while|n_act|remains >p2163. If it does, raisep2163by 5 % and retry. - Reduce the trip threshold for testing: set
p2166 = 1.0s andp2163 = 0.95 × n_ratedso that the next test triggers a fault, not a process stop. - Start the generator set, bring it to 50.0 Hz / 400 V, close the ATS, and observe the STARTER / AOP panel. The expected sequence is:
a) line dips, F07902 / F1370 may be masked byp1210 = 4;
b) drive enters fault pending for <p1212;
c) drive re-closes the line contactor, runs a flying search, re-engages the motor. - Use the trace function on
r0063(speed actual),r0070(DC link voltage) andr2169.7(stall status) to record the transient. Trigger the trace on a falling edge ofr0070< 540 V (typical 400 V system). - Restore
p2163to the recommended value (0.65 × n_rated) andp2166to 2.0 s. - Issue 5 consecutive changeovers in a 30-minute window; count any F1370 / F07902 that
p1210fails to clear. If > 0 events, increasep1211by 1 and re-test.
9. Verification
The changeover is acceptable when the following conditions are met during a 30-minute, 5-cycle test:
- Zero unacknowledged F1370 entries in the fault buffer (read with
r0945and the AOP / STARTER fault history). - Drive remains in Operation (r899 = 0x1F) through each transfer.
- Speed dip < 10 % of rated; recovery to setpoint < 2.0 s.
- DC-link voltage remains inside the band
p0280 < V_DC < p0284for > 99 % of the trace window. - Line contactor is not cycling (the G150's pre-charge circuit must be allowed to discharge between transfers – insert a 2 s dead time if the ATS is fast).
10. Edge Cases and Related Faults
| Fault | Meaning | Typical co-occurrence with F1370 | Remedy |
|---|---|---|---|
| F07900 | Motor blocked | Frequent – blocked detection is the SLVC fallback for F1370 | Tune p2174 – p2177 as for F1370 |
| F07901 | Motor speed overshoot | Rare on changeover; common on flying restart overshoot | Reduce p1202 and add p1465 damping |
| F30002 | DC-link undervoltage | Very common; precedes F1370 | Loosen p0280 as in Table 4 |
| F30003 | DC-link overvoltage | When generator AVR overshoots | Tighten AVR, raise p0284
|
| F07815 | Encoder signal lost (VECTOR) | Encoder cable chafed at the rotating part of the ATS | Inspect cable, p0492 for reaction |
| A07930 | Warning: motor stalled | Pre-fail flag; treat as F1370 in waiting | Same remedy; increase p2166 first to confirm cause |
p1210 = 1 and call the changeover "fixed" because F1370 no longer appears. What they have actually done is instruct the drive to acknowledge every fault, including ground faults (F30021), overcurrent (F30001) and brake failures. Use 4 or 6 – never 1.11. Mechanical / Process Considerations
The electrical fix is incomplete unless the mechanical side of the changeover is also consistent with it:
-
Load inertia. Calculate the deceleration rate during the worst-case dip.
t_dip ≈ J·Δω / T_mot. Ift_dip < 0.3 s, the rotor will not slow enough to leave thep2163window, and no parameter change is required – the dip is too short to matter. Ift_dip > 1 s, add a soft-start bypass or a flywheel. - Coupling. Rigid couplings transmit the rotor transient to the load and back. Flexible couplings with > 5° of twist help; belt drives do not.
-
Generator sizing. The generator should be sized at least 1.25 × the drive's apparent power:
S_gen ≥ 1.25 × √3 × V_LL × I_line / 1000. For a 400 V, 360 A line, this is ≥ 1.25 × √3 × 400 × 360 / 1000 ≈ 312 kVA. If 360 A is the single-phase feeder to the line filter, the value is multiplied by 3 / √3 = √3 to obtain a per-line estimate – verify the supply topology before sizing. -
ATS dead time. Adjust the ATS controller to give the G150 > 100 ms of dead time so that the DC link can discharge below
p0210 × √2before re-energising; this prevents the Active Line Module from latching a F30002 from an in-rush.
12. Alternative Topologies and Sizing Caveats
Some G150 sites are built with a bypass contactor arrangement (utility – bypass – generator). In that topology the drive can be disconnected from the motor during the transfer and the load is fed across-the-line directly. F1370 cannot occur in that case, but the motor is exposed to a DOL start with full inrush. Verify which topology you have; the parameter changes described above apply only to the in-line (utility – G150 – motor) topology, not the bypass topology.
kVA = √3 × V_LL × I / 1000. If 360 A is the rectifier DC-link current, the line current is approximately 0.816 × I_DC ≈ 294 A. The generator size must be re-calculated for whichever case the plant actually has. Label the assumption explicitly on the schematic.13. Quick-Reference Parameter Worksheet
Print this list and tick the values as they are set:
_____ p1200[0] = 4 ; Flying restart on ON command
_____ p1201[0] = r0863.0 ; Enable via drive enable, not ON/OFF1
_____ p1202[0] = 75 ; Search current (% of p0305)
_____ p1203[0] = 2.5 ; Search velocity factor
_____ p1207[0] = 1.0 ; Ramp time after catch
_____ p1210 = 4 ; WRA mode
_____ p1211 = 3 ; Attempts
_____ p1212 = 3.0 ; Wait time
_____ p1213 = 30 ; Monitoring window
_____ p1214 = 1 ; Restart on F1370
_____ p2163 = 0.65 × n_rated
_____ p2164 = 20 ; rpm hysteresis
_____ p2166 = 2.0 ; seconds
_____ p2167 = 0.5 ; seconds off-delay
_____ p2170 = 1.15 × I_mot_rated
_____ p0210 = 400 / 480 / 690 ; supply voltage
_____ p0211 = 50 / 60 ; supply frequency
_____ p0280 = 1.30 × √2 × p0210
_____ p0282 = –10 %
_____ p0283 = +10 %
_____ p0284 = 1.20 × V_DC_rated
_____ p3450 = 1 ; CW rotation only
14. Standards and References
For acceptance testing of the changeover, the relevant international reference is IEC 61800-2 (Adjustable speed electrical power drive systems – Part 2: General requirements – rating specifications for low voltage adjustable speed a.c. power drive systems). IEC 61800-2 § 6.4 covers ride-through behaviour and is the standard the G150 List Manual references for its test conditions; confirm with your local authority before claiming ride-through compliance.
15. Document History and Firmware Notes
-
V4.5 / V4.7 SP3:
p1200is single-indexed; some users have reported that the drive will not commitp1200 = 4unless the VSM10 is online – start the trace only after a successful pre-charge. -
V5.1 SP1 (current production line):
p1200is indexed per drive object and per dataset. The recommended valuep1200[0] = 4must be copied to all used datasets (DDS0 – DDS3) viap1621= 1. -
V5.3 (preview): adds smart flying restart under parameter
p1200 = 9with model-based search; if available, this is the preferred setting for unloaded or high-inertia applications, but it is not yet in the G150 List Manual (V5.1).
What does SINAMICS G150 fault F1370 mean?
F1370 is the SINAMICS G150 cabinet drive's "Motor stalled" fault. It is raised by the speed-monitoring function (p2163 / p2166) when the actual rotor speed falls below the threshold for longer than the configured time while the motor current is still above p2170. It commonly appears when the line supply is transferred between utility and generator.
What is the difference between F1370 and F07900 / F07902?
On the G150 the firmware routes the same physical condition to different fault numbers depending on firmware and control mode. F1370 is the cabinet-level signalling, F07900 is "motor blocked" (speed actual = 0, current high) and F07902 is "motor stalled" (speed actual below threshold, current high). All three are addressed by the same parameter family p2163 – p2170.
Which parameter should I change first to fix F1370 on a generator changeover?
Set p1200[0] = 4 (flying restart on ON command) and p1210 = 4 (WRA with fault acknowledgement) before loosening the speed thresholds. Most F1370 events on a 50 – 400 ms transfer are solved by these two changes alone. Only widen p2163 or lengthen p2166 if the drive reports F07902 / A07930 after the restart succeeds.
Is it safe to set p1210 = 1 to clear the F1370 fault?
No. p1210 = 1 acknowledges every fault without restarting. It hides the symptom of F1370 but also masks safety-relevant faults (F30021 ground, F30001 overcurrent). Use p1210 = 4 or 6; both issue a flying restart on the line returning and remain bound by the safety limits in the G150 List Manual.
Do I need a VSM10 module to fix F1370 on a generator changeover?
If the G150 is fitted with an Active Line Module, yes – the VSM10 is required for clean line synchronisation on the return of the generator supply. If the cabinet uses a Basic Line Module (B6U) the VSM10 is not present and the changeover must rely solely on flying restart and pre-charge timing; in that case extend p0223 (pre-charge time) to 5 – 8 s and keep p1211 ≥ 5.