A BiDi pig stopped at the ESD valve during an IP run on a 6-inch gas-lift line and was recovered from the launcher side. Treat the valve bore as the leading check, but inspect the complete transition through the ESD valve, adjoining pipe, and downstream ball valve. A valve marked full port can still have a smaller internal diameter than the connected pipe; a piggable installation calls for a full-conduit passage matched to the pipe ID.
Incident and Configuration Record
Before anything else, confirm the stopping location. A restriction near an ESD valve can originate in the valve bore, an incompletely open ball, a seat or seal protrusion, a flange mismatch, weld intrusion, debris, or the downstream valve. Retrieval from the launcher side identifies the direction of recovery but does not by itself prove which component stopped the pig.
- Record the BiDi pig body diameter, sealing-disc or cup diameter, minimum negotiable bore, allowable diameter reduction, and bend capability from its documentation.
- Record the actual pipe internal diameter on both sides of the ESD valve. Nominal line size alone does not define pipe ID.
- Identify every item in the local passage: reducers, flanges, welds, the ESD valve, and the downstream ball valve.
- Confirm the ESD valve and downstream valve were commanded open. Check local mechanical position indication as well as the remote open indication.
- Compare the reported stopping distance with the measured distance from the launcher to each possible restriction.
Do not move on until the stopping-distance record, pig dimensions, actual pipe ID, and local valve positions identify the passage that requires examination.
Datasheet and Nameplate Identification
Start the bore check with records because they can distinguish a reduced-port model without opening the line. The instrument datasheet for an ESD valve should include its port size. Cross-check that entry against the installed nameplate rather than relying on the tag description alone.
- Retrieve the ESD valve datasheet, purchase specification, certified drawing, and valve schedule.
- Read the installed valve tag, manufacturer, figure or model number, size, and serial number from the nameplate.
- Repeat the same identification for the downstream ball valve.
- Match the installed identifiers to the manufacturer’s catalog or certified dimensional drawing. Use the serial number when requesting official build details.
- Locate the minimum bore dimension, not merely a label such as
full portorfull bore.
| Record | Required field | Decision |
|---|---|---|
| Instrument datasheet | Port or bore size | Initial full- versus reduced-port classification |
| Nameplate | Figure/model and serial number | Identification of the installed build |
| Certified drawing | Minimum internal passage | Comparison with pipe ID and pig requirement |
| Pig documentation | Minimum negotiable bore | Pass/fail criterion for the route |
Calculate geometric clearance as clearance = minimum passage diameter − maximum pig outside diameter. This simple difference does not replace the pig supplier’s limits for disc deflection or abrupt steps. Do not move on until each document can be tied to the physical valve by its identifiers.
Full-Port and Full-Conduit Decision
The decisive dimension is the smallest unobstructed passage through the installed assembly. Reduced-port valves intentionally narrow that passage. Full-port or full-bore terminology can describe a manufacturer’s valve geometry without guaranteeing equality to the connected pipe ID. Full conduit means the opening is suitable for passage through the line and must be assessed against the actual pipe ID.
| Description | What it establishes | What remains to check |
|---|---|---|
| Reduced port | The valve contains an intentional bore reduction | Whether the pig can tolerate that reduction |
| Full port or full bore | The valve meets the manufacturer’s stated port configuration | Whether its minimum bore equals the connected pipe ID |
| Full conduit | The passage is specified for unobstructed line continuity | Actual diameter, alignment, and internal protrusions |
External body measurements and catalog dimensions can help separate full- and reduced-port models when the nameplate is readable. They cannot prove the internal diameter, ball condition, alignment, or absence of protrusions. The ESD valve must also reach its mechanical fully open stop; a permissive or limit-switch signal can be misadjusted and indicate open before the ball is aligned.
Do not move on until the documented minimum bore has been compared with both the pipe ID and the pig’s minimum negotiable bore.
Non-Intrusive Internal Examination
Use a camera or borescope when records are missing, contradictory, or unable to establish the installed condition. Access must permit a view through the ESD valve and downstream ball valve. Capture a dimensional reference in the image if bore measurement is required; an unscaled image can reveal a step or partially open ball but cannot establish clearance.
- Place the ESD valve and downstream valve in their required open positions under the site’s approved isolation controls.
- Insert the camera from an accessible opening and record the upstream transition, ball opening, seats, downstream transition, and adjoining valve.
- Look for a crescent-shaped ball obstruction, seat intrusion, debris, damage, offset bores, weld penetration, and abrupt diameter changes.
- Correlate each image with insertion distance so that any restriction can be assigned to a component.
Radiography is not the preferred first method for deciding whether this assembled valve is piggable. The heavy valve body, overlapping internal parts, projection angle, and lack of a direct dimensional reference can make the minimum free passage difficult to interpret. It may support a defined inspection objective when a qualified radiographic procedure can resolve the relevant geometry, but datasheets, certified drawings, valve identification, and direct visual examination give a clearer initial decision path.
Do not move on until the inspection shows a continuous open passage or identifies the exact location and form of the obstruction.
Intrusive Bore Confirmation and Correction
Pulling the valve provides the definitive check when documentation and non-intrusive inspection cannot establish the minimum passage. This requires line shutdown and isolation unless the installation has a usable bypass. Plan the examination for both the ESD valve and downstream ball valve so that one unverified restriction is not left in the route.
- Remove pressure and isolate the affected section under the approved site procedure.
- Remove the valve or gain direct access to its bore.
- Measure the minimum diameter through the ball, seats, and end connections, including any eccentricity or internal step.
- Confirm full mechanical travel and compare the actual ball position with the local and remote open indications.
- Compare the measured passage with the pipe ID and pig manufacturer’s minimum-bore requirement.
- If the bore is unsuitable, replace the valve with a correctly specified full-conduit valve or obtain an engineered modification. Machining a ball changes wall thickness, sealing geometry, balance, and pressure-containing design, so it requires the valve manufacturer’s or another qualified design authority’s approval rather than an uncontrolled machine-shop alteration.
Do not move on until the as-left valve configuration has a recorded minimum passage and the position indication agrees with the mechanical fully open position.
End-to-End Piggability Verification
Verification must cover the route, not just the component that first attracted attention. A corrected ESD valve will not prevent another stop at the downstream ball valve, an adjoining weld, or a mismatched transition.
- Create a bore schedule listing the actual pipe ID and minimum passage of every component in sequence.
- Compare every entry with the pig’s documented minimum negotiable bore and allowable transition geometry.
- Stroke each relevant valve and verify local mechanical position against the control-system indication.
- Confirm that inspection records show no seat intrusion, debris, damage, weld penetration, or offset at each transition.
- Use an approved proving method or test pig selected for the established passage before repeating the IP run.
- Record successful passage through the ESD valve and downstream ball valve at their verified fully open positions.
Frequently Asked Questions
Can I use radiography to tell whether an ESD valve is full bore?
Radiography may support a narrowly defined inspection, but it is not the first choice for measuring the free passage through an assembled valve. Check the datasheet, nameplate, certified drawing, and serial-number build details, then use a scaled camera inspection or direct measurement if the bore remains unresolved.
Does a full-port ball valve have the same ID as the pipe?
Not necessarily. Compare the valve’s stated minimum bore with the actual pipe ID; a piggable route requires adequate full-conduit clearance rather than reliance on the full port label.
Can an ESD valve show open and still stop a pig?
Yes. A misadjusted position switch can report open before the ball reaches its mechanical stop, and seats, damage, debris, or an offset transition can still project into the passage. Verify mechanical position locally and inspect the internal opening.
Does checking only the ESD valve prove the line is piggable?
No. Record the minimum passage through the ESD valve, downstream ball valve, welds, flanges, and transitions, compare each with the pig’s documented limit, and finish by recording successful passage through the complete verified route.