Short answer

Keep WinCC as a written requirement in the purchase specification, with the edition, the license owner and the source-project deliverables named. Give the S7-1500 a symbolic interface over OPC UA so the SCADA stays replaceable without PUT/GET access. Accept a supplier-built platform only when it passes written documentation, reference and license checks.

On this page
  1. Why should new furnaces stay on WinCC instead of the supplier's platform?
  2. What must the purchase specification say to lock in WinCC?
  3. How do you keep the S7-1500 interface replaceable for any SCADA?
  4. When does a supplier SCADA force PUT/GET, and what does enabling it cost?
  5. What written evidence must a supplier-built SCADA pass?
  6. Which project files and people must the contract secure?
  7. What is the final decision for each case?
  8. Questions asked

Your instinct is right, and it is also the engineering answer: keep WinCC. The S7-1500 does the control work whichever SCADA draws the screens, so this is a procurement and interface decision, not a control decision, and you can make it stick with three moves. Write the WinCC edition, the license ownership and the source-project deliverables into the purchase specification. Keep the PLC interface symbolic, served over OPC UA rather than PUT/GET, so the operator layer stays replaceable. And gate the supplier's in-house platform on written documentation, contactable references and licenses issued to you — a gate a small platform rarely passes.

Why should new furnaces stay on WinCC instead of the supplier's platform? #

Stay with WinCC: the furnaces you already run use it, your people know it, and a platform built inside one supplier's network has a support base equal to the handful of engineers who wrote it. Treat the operator layer as a 15 to 20 year asset, because that is how long a furnace line stays in service, and count who can support it over that horizon. With WinCC you have trained people in-house, a large integrator market, versioned documentation and a vendor migration path; with the in-house platform you have one team whose availability you do not control. The PLC program is unaffected either way, which is why this argument is winnable: you are not asking the supplier to change the controls, only the visualization package. Long quoted lead times from furnace builders are a reason to be precise in the contract, not a reason to accept a substitute.

What must the purchase specification say to lock in WinCC? #

Name five things in writing: the WinCC edition and engineering tool version, who buys the engineering and runtime licenses, the source-project deliverables, the acceptance tests, and a clause that any platform substitution needs your written approval. A letter that says to treat WinCC as a project requirement is the minimum; contract text is what survives contact with a supplier who has a platform to place. Write these as scope items:

  1. Edition and version. Match the edition your existing furnaces run and record the TIA Portal version. WinCC runtime licenses are commonly sized by tag count, so state the tag tier the project needs. Engineering and runtime are separate items, and why a WinCC Professional entry does not mean a runtime is installed explains the difference before anyone counts an installed package as a license.
  2. License ownership. Both the engineering and the runtime licenses are bought in your organization's name, even when the supplier does the installation and configuration.
  3. Deliverables. The complete source project, not a compiled runtime; the tag list; the alarm list; the recipe definitions; the screen inventory. Anything less sends every future edit back to the supplier.
  4. Acceptance tie-in. The archive restore test described below is an acceptance item, passed at factory acceptance and repeated at site acceptance.
  5. Change clause. Any substitution of SCADA platform requires your written approval, and the schedule and commercial consequences of a substitution sit with the supplier.

How do you keep the S7-1500 interface replaceable for any SCADA? #

Require three things from the PLC program: optimized blocks with symbolic tags for everything the SCADA touches, a published interface document listing each tag with data type, unit, range and direction, and OPC UA as the access path. Build the data as user data types — one per furnace zone, heater group, thermocouple channel and alarm set — with symbolic names that match the delivered tag list, so a zone is extended by adding an instance, not by renumbering addresses. Optimized blocks give symbolic access and are what the CPU's OPC UA server publishes. If the SCADA reads absolute addresses instead, those blocks must lose optimization, and every future platform change re-engineers the PLC.

Prove the interface before acceptance: browse the CPU from an independent OPC UA client on a test laptop and confirm every listed tag resolves by name with the documented type and unit, with no manual address entry. Browsing is half the proof; values must also arrive, and what to check when OPC UA browsing works but runtime gets no values covers that failure. If a configured runtime still will not see the CPU, fixing a WinCC Professional runtime that will not connect to the S7-1500 walks the connection path.

When does a supplier SCADA force PUT/GET, and what does enabling it cost? #

Any client that talks the raw S7 protocol to an S7-1500 needs the CPU option Permit access with PUT/GET communication from remote partner switched on, and that option opens the CPU to unauthenticated remote reads and writes. You find it in the CPU properties during device configuration, under Protection & Security > Connection mechanisms, beside the access level you set for the CPU; the Siemens support entry documents it for S7-1500 CPUs from firmware V3.1. Two costs come with it. First, PUT/GET reaches only standard-access blocks, so every block the client reads must have optimization turned off — which is the interface problem from the previous section. Second, those reads and writes arrive with no authentication, so the option weakens the protection level you configured. These CPUs run burners and heaters; a control CPU that accepts unauthenticated remote writes is an exposure to design out, not to manage.

OPC UA avoids both costs: it serves the symbolic tags of optimized blocks and supports user authentication and encryption. What it requires is a license — a license is needed to run the S7-1500's OPC UA server, one license per CPU, with the class chosen by CPU performance.

Worked example, with example inputs: one hall, six furnaces each on its own S7-1500 CPU, plus one shared handling CPU the SCADA also reads. PUT/GET route: 6 + 1 = 7 CPUs with the option enabled and their exposed blocks converted to standard access. OPC UA route: 6 + 1 = 7 CPUs x 1 license = 7 OPC UA server licenses, with the access protection levels untouched. Decision: buy the 7 licenses, because a license is a known line item you budget once, while weakened protection on a furnace CPU is not something you fix by spending later.

What written evidence must a supplier-built SCADA pass? #

Require five written answers before the platform is evaluated at all: versioned documentation, contactable reference sites, a named maintenance team with a support commitment, licenses issued to your organization, and a documented patch and operating-system compatibility policy. A competitor running the same platform verifies nothing, because you cannot call them and ask. Send the table as a formal request and accept only written answers with documents attached.

Risk What you request An acceptable answer
Thin documentation Engineering manual, configuration guide, interface specification Versioned documents covering installation, tag and alarm configuration, and backup and restore
Small install base Named installations you may contact, with runtime hours Multiple sites unrelated to the supplier, at least one running a furnace or batch thermal process
Single-team dependency Who maintains it, how many people, what happens when they leave A written support commitment with response times, plus source-code escrow or an equivalent
License ownership Who owns the runtime and engineering licenses Licenses issued to your organization, with no recurring fee needed to keep running
Update path Operating system and security patch policy A documented compatibility statement for the Windows version you will deploy

Verbal assurances fail the gate. A supplier that cannot answer these items in writing has already answered the question the table asks.

Which project files and people must the contract secure? #

Put one name, one version record and one file set into the contract: the WinCC programmer as the individual or a qualified equivalent, the exact engineering tool versions, and the complete project archives delivered at factory acceptance and again at site acceptance. Buying the same product again does not restore knowledge that lives on one person's engineering PC; the contract and the archives do. Work through four items:

  1. Name the programmer. The individual who programmed the earlier furnaces, or a qualified equivalent, with a contracted route for engaging that person directly if the supplier cannot field the resource.
  2. Record the tool versions. The exact TIA Portal and WinCC versions travel with the archive, and what STEP 7 is in a PLC project and which one you need explains how those engineering tools fit together.
  3. Take the archives twice. Full project archives at factory acceptance and again at site acceptance, after the last changes.
  4. Store and restore yourself. The archives go into your own repository with versioned backups, and a restore onto a clean engineering PC that has never held the project must open the project, compile it without errors and download it to a test CPU or a simulation. A project that opens only on the supplier's machine has not been delivered.

What is the final decision for each case? #

WinCC stays the requirement: write it into the specification, serve it over the symbolic OPC UA interface, and take the archives — and the supplier's platform replaces it only after it passes all five evidence gates in writing. Apply it to the three situations you actually face:

  1. The supplier signs the specification as written. Proceed with the order: put the OPC UA licenses on the buy list, keep PUT/GET off every CPU, and schedule the archive restore at both acceptance stages.
  2. The supplier pushes its own platform. It must pass the five gates with documents attached; a thin-documentation, small-install-base platform will not, and the answer is no. Resolve this before design freeze, because a substitution accepted late is a substitution accepted for good.
  3. The individual programmer is unavailable. The qualified-equivalent clause and the delivered archives carry the knowledge forward; that is the whole reason both are in the contract.

One architecture, one tool chain, one set of archives you own — that is what keeps the next hall of furnaces as supportable as the last one.

Questions asked

Does the OPC UA server run on every S7-1500 CPU?

Not unconditionally. The server needs a license for each CPU, the license class depends on CPU performance, and some OPC UA functions require a higher firmware and a higher TIA Portal version than the base functions. Check the Siemens documentation for your exact CPU and firmware before the interface is written into a purchase specification.

Does WinCC itself need the PUT/GET option to read an S7-1500?

No. WinCC in TIA Portal connects through configured HMI connections and symbolic tags on optimized blocks, so the PUT/GET option stays off. The option becomes necessary only when a third-party or home-grown client speaks the raw S7 protocol with absolute addresses.

Can an existing line move from PUT/GET to OPC UA later?

Yes, as a controlled change. Convert the exposed blocks to optimized access, map the client's absolute addresses to symbolic tags, verify every tag, then clear the PUT/GET option and download. Clients still on the S7 protocol lose their connection at that moment, so schedule the cutover with the furnace stopped and prove it on the bench first.

Who should hold the WinCC licenses when the supplier does the installation?

Your organization, in its own name, for both engineering and runtime. Licenses held by the supplier tie the software to that company: if the relationship ends, you can be left with furnaces whose SCADA you cannot legally run or re-engineer. The supplier installs and configures; you own.

Keep reading

  • Troubleshooting

    When WinCC OPC UA browsing works but runtime gets no values

    Successful tag browsing and installed certificates prove only that WinCC reached the bridge's address space. Commission the link as four boundaries — upstream data into the bridge, the OPC UA session, the tag mapping, runtime updates — with one known test item, and stop at the first boundary that fails; it names the fix.

    HMI and touchscreens

  • Comparison

    Logging PLC Data to SQL: Use a Gateway, Not the HMI

    Neither the S7-1200 nor a Comfort panel can be the SQL client: enabling OPC UA or loading MQTT blocks moves data, it does not commit transactions. Serve the logging tags from the S7-1200 over OPC UA and let a gateway beside the customer's database write the rows, keep the panel's CSV logging as the staged first move, and bench-test any direct-SQL library against the full 30-column record before purchase.

    Industrial networks

  • Explainer

    Why WinCC V6 Needs an OPC Server to Reach an S7-200 PPI Port

    WinCC V6.0 SP4 carries no channel that can open the S7-200's PPI port directly. The supported route is an OPC server — SIMATIC NET or KEPServerEX — owning the PLC leg, with WinCC reading the server's items as the client.